When a Tunnel Can’t Stop: 1,075 kWh Mobile Power Keeps Grouting Crews Running

No road-closure permits, no diesel, no interruption — how a mobile storage solution held a 500 kW continuous load for a tunnelling project on a compressed schedule.

When a Tunnel Can’t Stop: 1,075 kWh Mobile Power Keeps Grouting Crews Running
Mobile storage equipment supporting continuous tunnel-grouting operations.
1,075 kWhSINGLE-UNIT CAPACITY
500 kWCONTINUOUS LOAD
6–7 HOPERATING WINDOW
01

Power could not wait

The tunnelling programme was compressed and its grouting equipment needed immediate, continuous power. A delay or interruption would directly affect the project schedule.

02

Conventional options were blocked

  • A mains extension required road occupation and lengthy permits
  • Diesel generation conflicted with cost, noise and emissions constraints near residents
03

The hard operating constraint

The stable operating load was 500 kW. Each grouting cycle ran for 6–7 hours and could not tolerate an interruption longer than about 15 minutes without risking set grout, damaged equipment and rework.

04

Mobile storage sized to the duty

Two 1,075 kWh units operated in parallel for the active load, with two matching units configured as on-load standby.

05

Seamless transfer

Rotation and standby switch-in were organised without interrupting supply, matching the grouting equipment’s requirement for stable, fluctuation-free power.

06

Why the approach worked

  • No on-site exhaust and substantially lower noise
  • Fast deployment without lengthy grid construction
  • High-power coverage for the full grouting window
  • Redundant units for continuous operation
01

供电不能等待

隧道项目工期紧凑,注浆设备需要立即获得连续电力;延迟或中断都会直接影响施工计划。

02

常规方案受限

  • 市电延伸需要占用道路并经历较长审批
  • 柴油发电在居民区附近受到成本、噪声与排放条件限制
03

不可妥协的运行条件

现场稳定负载为 500 kW。单次注浆连续运行 6 至 7 小时,停电超过约 15 分钟可能造成浆液凝固、钻头卡死、设备损伤与返工。

04

按工况配置移动储能

两台 1,075 kWh 设备并联承担当前负载,另配置两台同规格设备作为带载备用。

05

无缝切换

运行机组轮换与备用设备切入过程中保持供电连续,满足注浆设备对稳定、无波动电力的要求。

06

方案价值

  • 现场无尾气并显著降低噪声
  • 无需漫长电网施工即可快速部署
  • 覆盖完整注浆作业窗口的高功率需求
  • 通过冗余设备保障连续运行
BACK TO NEWS